Friday, July 25, 2014

MODOT provides update on 171/43 roundabout

(From MODOT)

Route 171/Route 43 Roundabout Construction
Update for Week of July 28, 2014
 
Work scheduled:
  • Applying permanent lane stripes (weather permitting)
  • Roundabout scheduled to open to two lanes by Wednesday morning (pending permanent lane striping)
  • Building concrete islands
  • Landscaping the center of the roundabout
  • Installing overhead sign trusses at night
  • Applying grass seed and mulch
  • Cleaning up in areas
Weather and/or construction delays will alter the work schedule.
Traffic Impacts:
  • Lane closing possible at times
  • At least one lane open in each direction at all times