(From MoDOT)Davis Blvd. CLOSED in Joplin for Relocation Project Beginning Sept. 30
Where: Davis Boulevard between 27th Street and Route FF (32nd Street) in Joplin
When: Wednesday, September 30 for the duration of the project
What: Contractor crews CLOSING Davis Boulevard as part of a project to relocate the street approximately 1,000 feet to the east and connect it with Stephens Boulevard
Traffic Impacts
Davis Boulevard CLOSED between 27th Street and Route FF (32ndStreet) in Joplin
Access to the General Mills facility will be maintained throughout the project
Traffic will be directed along a signed detour using Route FF (32ndStreet), Range Line Road and 20th Street
Drivers urged to find alternate routes
Signs and message boards will alert drivers approaching the work zone
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or scheduling conflicts could alter the work schedule.
Additional Details
The work to relocate Davis Boulevard is to make room for a future project to build a bridge over the Canadian Pacific Kansas City (CPKC) Railroad at Route FF (32nd Street).
Project Information
Project Information
Prime contractor: Hartman & Company Inc., Springfield
Total project cost: $2.9 million
Completion date: December 1, 2026
Total project cost: $2.9 million
Completion date: December 1, 2026