Pavement sealing work scheduled in Jasper, Newton, Barton counties

(From MODOT)

Pavement Sealing Work Scheduled for Various Routes in Barry, Jasper, Newton,
Stone, Barton, Christian, Taney & Lawrence Counties Beginning Week of July 1


MoDOT Southwest District – Seven state routes – in Barry, Jasper, Newton, Stone, Barton, Christian, Taney & Lawrence counties – are scheduled to be sealed with a mixture of rock and oil beginning the week of July 1, the Missouri Department of Transportation said.

Here’s a look at the locations and the tentative schedule:
Missouri Route 86 in Stone County from Route 13 in Blue Eye east approximately 12 miles to the roundabout at Big Cedar Lodge in Taney County – mid July
Missouri Route 86 beginning at the Barry/Stone county line east approximately 10 miles to Missouri Route 13 in Stone County – late July
Missouri Route 265 in Stone County from Route 76 in Reeds Spring approximately 13 miles to near Chateau on the Lake in Branson – late July
Missouri Route 265 in Lawrence County from U.S. Route 60 in Marionville approximately 31 miles to Branson West – late July
Missouri Route 413 in Christian County from U.S. Route 60 near Billings south approximately four miles to Missouri Route 265 – early August
Business Route 37 in Barry County from Missouri Route 37 to 5thStreet in Cassville – early August
Newton County Route NN at Reddings Mill south approximately 11 miles to Kapok Drive – mid August
Missouri Route 86 in Newton County from the roundabout at East 50th Street in Joplin south approximately one mile to Broad Lawn Circle – mid August
Missouri Route 43 in Jasper County from the roundabout at Missouri Route 96 north approximately 14 miles to Missouri Route 126 in Barton County – late August
Missouri Route 126 in Barton County from the Missouri/Kansas state line approximately 30 miles east to U.S. Route 160 at Golden City – late August

Weather and/or construction delays could alter the work schedule

Drivers can expect one-lane traffic with flaggers and pilot vehicles directing them through the work zone. Traffic could be stopped for several minutes. Delays are expected.

Drivers are urged to use caution and reduce their speed when traveling over recently-sealed sections of highways.

A chip-seal is planned for these roads as an economical way to maintain and preserve the roadway. The treatments keep a road from deteriorating and will extend its life.

Project information:
Contractor: Blevins Asphalt Construction Co., Mt. Vernon
Total cost: $2.2 million
Completion date: November 1, 2017