TRAFFIC ALERT: New Jasper County Route D/Center Creek Bridge at Oronogo OPEN to Traffic
When: 4:15 p.m., Friday, March 13
Details: Contractor crews finished work to build new Route D bridge over Center Creek
Project details
Project replaced old truss bridge with new higher and wider bridge with no truss at Oronogo.
The bridge was originally closed in April 2019. Completion was delayed due to weather and unforeseen construction issues.
Total project cost: $3 million
Prime contractor: Hartman & Company, Springfield