Contractor crews will lay a new asphalt surface along an approximately 1.7-mile stretch of Route MM between Missouri Route 96 and Jasper County Route D in Oronogo.
Traffic Impacts
-Drivers will encounter pilot cars where crews are working. Drivers should wait for the pilot vehicle before proceeding through the work zone or before entering the work zone from a side road.
-Use caution when traveling through the work zone and watch for crews and equipment on the road
-No signed detours
-Drivers are urged to find alternate routes around the work zone
-Signs and message boards will alert drivers to the work zone
Weather and/or construction delays will alter the work schedule.
This is part of a larger project that includes resurfacing Jasper County routes M and H and Newton County Route CC. Routes M and H have been completed and are open to traffic. More information about Route CC will be announced closer to the start of that project.
Project Information
Prime contractor: Emery Sapp & Sons, Columbia
Total project cost: $2.2 million
Completion date: November 1, 2020