Monday, July 31, 2017

Construction 10 days ahead of schedule on Carl Junction bridge

(From the Carl Junction Police Department)

Update on the bridge (on 171 over Center Creek) project- The construction crew is 10 days ahead of schedule. 

The beams to run across the piers are going to be delivered, probably Wednesday. The Highway Patrol has to escort them as one of their "super load" details. The beam are 133' and precast. They will be installed right off the truck onto the piers. There will be 20 of them total.

No comments:

Post a Comment