Work scheduled:
Pour concrete for new off- and on ramps on eastbound I-44/I-49 at Prigmor Avenue (CR 190) during overnight hours May 26, 27 & 28
Grade rock and dirt for new I-44/I-49 lane addition and south roundabout on Prigmor Avenue (CR 190)
Build new bridge column in I-44/I-49 median
Complete construction of retaining wall on south side of I-44/I-49
Build retaining wall on north side of I-44/I-49
Pave shoulder along south retaining wall
Traffic Impacts:
No work planned on project over the Memorial Day weekend (noon Friday, May 22, until 9 a.m. on Tuesday, May 26)
20th Street at Prigmor Avenue (CR 190) CLOSING on Thursday, May 21, for duration of the project
One eastbound lane and one westbound lane of I-44/I-49 CLOSED at Prigmor Avenue (CR 190). Work hours: 6 p.m. to 7 a.m., Tuesday, Wednesday and Thursday, May 26-28.
Prigmor Avenue bridge (CR 190) CLOSED over I-44/I-49 until fall.
Apple Road CLOSED at Prigmor Avenue (CR 190) for duration of the project. Drivers can access Apple Road via CR 180 and CR 170 north from Route FF (32nd Street).
Narrowed lanes on I-44/I-49 for the duration of the project.
At least one lane of traffic open in each direction on I-44/I-49.
Weather and/or construction delays will alter the work schedule.
Project Background:
Build interchange at Prigmor Avenue (Jasper County Road 190) over I-44/I-49 with ramps connecting to the interstate
Build roundabouts on each end of bridge over I-44/I-49 to connect ramps to Prigmor Avenue
Resurface and add two foot shoulders on Prigmor Avenue between new interchange and 7th Street (Route 66) to the north
Prime Contractor: Emery Sapp & Sons, Inc., Columbia
Total Project Cost: $8.6 million
Completion Date: November 1, 2015
Partnership Project: Jasper County, City of Duenweg, City of Joplin, Crossroads Business and Distribution Park
|