(From MoDOT)
Lane Reductions, Delays on Route 60 in Newton Co. for Pavement Repairs Beginning Week of June 17
Drivers can expect narrowed lanes and delays on U.S. Route 60 and Missouri Route 59 in Newton County for pavement repair beginning the week of June 17, the Missouri Department of Transportation said.
Here is what drivers can expect during the project:
Where:S. Route 60 from a point east of I-49 to Missouri Route 59 through Neosho
Traffic Impacts
Traffic reduced to one lane where crews are working
Work will be done during nighttime hours, 7 p.m.-7 a.m., Monday-Friday
Expect delays during high traffic volume times
Signs and message boards will alert drivers approaching work zone
No signed detour
Drivers should find alternate routes around work zone
Check MoDOT’s Traveler Information Map for road closings/traffic impacts
Weather and/or construction delays could alter the work schedule.
Project Information:Prime Contractor – Branco Enterprises, Springfield
Project Cost - $829,000
Contract Completion Date: November 1, 2024