(From MODOT)
Crossroads Interchange Construction
Update for Week of March 30, 2015
Work scheduled:
Remove existing shoulders on eastbound I-44/I-49
Lay drain pipe north of I-44/I-49
Extend drain pipes behind barrier walls along I-44/I-49
Begin dirt work for new south roundabout ramp at Apple Road
Traffic Impacts:
Apple Road CLOSED at Prigmor Avenue (CR 190) for duration of the project. Drivers will have access to Apple Road via CR 180 and CR 170 north from Route FF (32ndStreet).
Nighttime lane closings on I-44/I-49 in the area of Prigmor Avenue. Work hours 7 p.m. to 6 a.m.
Narrowed lanes on I-44/I-49 for the duration of the project.
At least one lane of traffic open in each direction on I-44/I-49.
Weather and/or construction delays will alter the work schedule.
Project Background:
Build interchange at Prigmor Avenue (Jasper County Road 190) over I-44/I-49 with ramps connecting to the interstate
Build roundabouts on each end of bridge over I-44/I-49 to connect ramps to Prigmor Avenue
Resurface and add two foot shoulders on Prigmor Avenue between new interchange and 7th Street (Route 66) to the north
Prime Contractor: Emery Sapp & Sons, Inc., Columbia
Total Project Cost: $8.6 million
Completion Date: November 1, 2015
Partnership Project: Jasper County, City of Duenweg, City of Joplin, Crossroads Business and Distribution Park