Saturday, July 4, 2015

MODOT provides Crossroads Interchange update

Crossroads Interchange Construction
Update for Week of July 6, 2015
 
Work scheduled:
  • Pouring concrete for eastbound on ramp onto I-44/I-49 during nighttime hours July 6
  • Grading along north side of I-44/I-49
  • Pouring concrete for widening of westbound I-44/I-49 lanes during nighttime hours July 8
  • Pouring concrete for Apple Road, Prigmor Avenue (CR 190) and south roundabout
  • Building forms to prepare for pouring of concrete for driving surface on new bridge
  • Pouring concrete for driving surface on new bridge morning of July 8
  • Grading base rock along north and south side of I-44/I-49
Traffic Impacts:
  • Right eastbound lane on I-44/I-49 CLOSED between 6 p.m., Monday, July 6 and 7 a.m., Tuesday, July 7 to pour concrete for eastbound on ramp
  • Right westbound lane on I-44/I-49 CLOSED between 6 p.m., Wednesday, July 8 and 7 a.m., Thursday, July 9 to pour concrete for widening of lanes
  • 20th Street at Prigmor Avenue (CR 190) CLOSED for duration of the project
  • Prigmor Avenue bridge (CR 190) CLOSED over I-44/I-49 until fall
  • Apple Road CLOSED at Prigmor Avenue (CR 190) for duration of the project. Drivers can access Apple Road via CR 180 and CR 170 north from Route FF (32nd Street)
  • Narrowed lanes on I-44/I-49 for the duration of the project
  • At least one lane of traffic open in each direction on I-44/I-49
Weather and/or construction delays will alter the work schedule.