Wednesday, June 18, 2014

Construction update on 171/43 roundabout

(From MODOT)

Route 43/Route 171 Roundabout Construction
Update for Week of June 23, 2014
 
Work scheduled:
  • Nighttime paving begins on Route 43 & Route 171
  • Daytime grading and paving entrances and street approaches in various locations
Weather and/or construction delays will alter the work schedule.
Traffic Impacts:
  • Nigthttime lane closings at times between 7 p.m. and 6:30 a.m.
  • At least one lane of traffic open in each direction at all times
Project Background:
  • Build two-lane roundabout at Route 171/Route 43 intersection in Airport Drive
  • Widen Route 171 to five-lanes (two lanes in each direction with a center turn lane) between Route 43 to just east of Fir Road
  • Prime Contractor: APAC, Springfield
  • Completion Date: August 28, 2014
  • Construction Cost: $2.6 million

No comments:

Post a Comment