MODOT offers update on Crossroads Interchange

Crossroads Interchange Construction
Update for Week of September 21, 2015
 
Work scheduled:
  • Pouring concrete on north side of I-44/I-49 for westbound on ramp
  • Widening and paving on north Prigmor Avenue
  • Applying grass seed and mulch throughout the project
  • Installing guardrails in the median
  • Final cleanup around auxiliary lanes
Traffic Impacts:
  • Some lane closings for pavement repairs on north end of Prigmor Avenue on the existing asphalt
  • 20th Street at Prigmor Avenue (CR 190) CLOSED for duration of the project
  • Apple Road CLOSED at Prigmor Avenue (CR 190) for duration of the project
  • Drivers can access Apple Road via CR 180 and CR 170 north from Route FF (32ndStreet)
  • Both eastbound and westbound auxiliary lanes scheduled to open west of the bridge
  • At least one lane of traffic open in each direction on I-44/I-49
Weather and/or construction delays will alter the work schedule.