Saturday, September 12, 2015

MODOT provides Crossroads Interchange update

(From MODOT)

Crossroads Interchange Construction
Update for Week of September 14, 2015
 
Work scheduled:
  • Pouring concrete on north side of I-44/I-49 on 20th Street, Prigmor Avenue and ramps
  • Completing work on new I-44/I-49 auxiliary lanes
  • Repairing asphalt pavement on north Prigmor Avenue
  • Grading dirt in the median of I-44/I-49
  • Installing guardrails in the median
  • Installing street lighting on south side of I-44/I-49
  • Applying grass seed and mulch throughout the project
Traffic Impacts:
  • Some lane closings for pavement repairs on north end of Prigmor Avenue on the existing asphalt
  • New I-44/I-49 auxiliary may open to traffic sometime during the week
  • 20th Street at Prigmor Avenue (CR 190) CLOSED for duration of the project
  • Apple Road CLOSED at Prigmor Avenue (CR 190) for duration of the project
  • Drivers can access Apple Road via CR 180 and CR 170 north from Route FF (32ndStreet)
  • At least one lane of traffic open in each direction on I-44/I-49
Weather and/or construction delays will alter the work schedule.
Project Background:
  • Build interchange at Prigmor Avenue (Jasper County Road 190) over I-44/I-49 with ramps connecting to the interstate
  • Build roundabouts on each end of bridge over I-44/I-49 to connect ramps to Prigmor Avenue
  • Resurface and add two foot shoulders on Prigmor Avenue between new interchange and 7th Street (Route 66) to the north
  • Prime Contractor: Emery Sapp & Sons, Inc., Columbia
  • Total Project Cost: $8.6 million
  • Completion Date: November 1, 2015
  • Partnership Project: Jasper County, City of Duenweg, City of Joplin, Crossroads Business and Distribution Park